Abuja-Kano Road Contract: Reps Threaten To Revoke Contract

Afnews Editor

Aug 28, 2020

The House of Representatives Committee on Works has threatened to demand revocation of the Abuja-Kaduna-Abuja road contract due to delays in its execution by Julius Berger PLC.

READ ALSO: How a Catholic Priest Slumped and Died While Delivering Homily in Delta Church

The committee said it might be forced to ask the government to re-award the contract to several other contractors to ensure that the project is completed within the life span of the current administration.

READ ALSO: "Ikwuano Locked Down For Alex Otti" - Monday Ubani SAN Sends Strong Message To Opposition

The committee expressed disappointment with the pace of work in the Abuja-Kaduna road nine months to expiration of the deadline for completion.

READ ALSO: Bloodbath At Wedding: Bandits Kill 13, Abduct Many In Midnight Attack In Kaduna Community

The committee members were particularly disappointed after about 27 months since the commencement, less than 10 percent of the work has been completed.

READ ALSO: How Gas explosion killed two in Akwa Ibom

Chairman of the House Committee on Works, Abubakar Kabir Abubakar (APC, Kano), who spoke while inspecting the project as part of the Committee's oversight function, however told the contractors Julius Berger they must deliver on the contract by May 2021, which is the terminal date for the contract.

READ ALSO: Marc Guehi: Man City sign defender from Crystal Palace for an initial £20m as spending reaches £425m in 12 months

He said the House will not accept any extension of the completion date or a variation of the project, adding it was disappointing there no satisfactory progress on the work.

READ ALSO: Boundary Dispute (Isu Case): Abia, Cross River Lawmakers Meet

However, the North Central Zonal Director of Works in the Federal Ministry of Works, Engr. Kunle Yusuf, told the Committee that 40 percent of the work on section one of the project covering about 62 kilometres has been completed even when work was yet to commence on over 100 kilometers of the road.

READ ALSO: Nigeria Slips Into Another Recession Under President Buhari |READ FULL FOR DETAILS

Section one of the Project is about 165 kilometers.

READ ALSO: Buhari@79: You've Been An Inspiration To Nigeria & Africa- Hope Uzodinma | READ DETAILS

Kabir said despite lack of funding for the project as attested to by the contractors, they have not shown any form of seriousness in completing the project saying "N155 billion is no small money".

READ ALSO: Ofuji Ndị Igbo Sets 2026 Agenda, Promises Greater Community Engagement

He said if the company lacks the capacity to deliver the project on schedule, it should be revoked and re-awarded to several other companies so that it will be completed on schedule.