Total closure of Third Mainland Bridge from midnight Saturday

chuks oti

Dec 22, 2020

The Third Mainland Bridge in Lagos will be totally shut for 72 hours from midnight Saturday, Federal Controller of Works, Olukayode Popoola said.

READ ALSO: BREAKING: Osun directs schools to revert to old names

The closure is to allow for casting of concrete on the expansion joints.

READ ALSO: United Abia Artists and Patriots (UAAP) Condemns Kano Court Ruling

Popoola said that the shutdown will last till midnight on Tuesday.

READ ALSO: How a Catholic Priest Slumped and Died While Delivering Homily in Delta Church

Repair work on the bridge began late July and was to end in January.

READ ALSO: Ofuji Ndị Igbo Sets 2026 Agenda, Promises Greater Community Engagement

The deadline has now been shifted till February, because of the #EndSARS protest.

READ ALSO: Mother's Day: Abia Government Liaison Officer Honours Women, Says Mothers Shape Future Leaders

Popoola said construction work had reached the stage for casting concrete on additional three expansion joints.

READ ALSO: Bloodbath At Wedding: Bandits Kill 13, Abduct Many In Midnight Attack In Kaduna Community

"There is going to be total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane

READ ALSO: "Ikwuano Locked Down For Alex OttiÔÇØ - Monday Ubani SAN Sends Strong Message To Opposition

ÔÇØ The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.

READ ALSO: Why ICPC Is Prosecuting Mike Ozekhome Over a London Property Deal That Has Shaken Nigeria's Legal Circle | READ DETAILS

"By the time the Christmas is winding down which is 12:00 midnight, we are going to close it so that we will be able to cast the concrete on Saturday the 26th and 27th we cast again.

READ ALSO: Ikpeazu emerges 2019 Vanguard Newspaper Governor of the Year

ÔÇØ And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure.

READ ALSO: EPL: 3 Midfielders To Leave Stamford Bridge As Chelsea Lead In Race To Sign £128m Midfielder

"This is to prevent vibration of the bridge. If we allow vehicles to be moving on one lane, there is going to be vibrations and the concrete will not set properly,ÔÇØhe said.

READ ALSO: Abiapoly: Ikpeazu Convokes Summit To Resolve Challenges

The controller said that all the alternative routes were in good condition and traffic regulatory agencies had been deployed to effectively divert and manage traffic to avert gridlock.

READ ALSO: Ikpeazu Present N147b Economic Recovery Budget, Gives Details, Lauds Abia Assembly

He appealed to road users to cooperate with traffic regulatory agencies.

READ ALSO: BREAKING: Osun directs schools to revert to old names

Repairs on the bridge was initially divided into two phases of three months on each carriageway, starting with the Oworonsoki bound carriageway.

READ ALSO: United Abia Artists and Patriots (UAAP) Condemns Kano Court Ruling

The work dragged into four months.

READ ALSO: How a Catholic Priest Slumped and Died While Delivering Homily in Delta Church

Traffic was partially diverted on a stretch of 3.5km where construction is ongoing between Adeniji Adeniji Ramp and Ebute Meta, while different time belts were allotted for traffic diversions on the bridge.

READ ALSO: Ofuji Ndị Igbo Sets 2026 Agenda, Promises Greater Community Engagement

The 11.8km bridge is the longest of the three bridges connecting Lagos Island to the Mainland.

READ ALSO: Mother's Day: Abia Government Liaison Officer Honours Women, Says Mothers Shape Future Leaders

The bridge starts from Oworonshoki, which is linked to the Apapa-Oshodi Expressway and the Lagos-Ibadan Expressway and ends at the Adeniji Adele Interchange on Lagos Island.

READ ALSO: Bloodbath At Wedding: Bandits Kill 13, Abduct Many In Midnight Attack In Kaduna Community

Constructed in 1990, the bridge was adjudged as the longest in Africa until 1996 when the Oct. 6 Bridge in Cairo, Egypt was completed.