Why Osisioma Flyover Is Yet Not Delivered - Abia Govt Reveals
Afnews Editor
Aug 19, 2021
Abia State Commissioner for Information, Chief John Okiyi Kalu has just revealed why Osisioma Flyover is yet to be delivered as planned. The details of the reason is contained in a publication made available to ALL FACTS NEWSPAPER.
READ ALSO: Birthday: Emenike Iroegbu Celebrates Ikechukwu Emetu, Praises His Support for Otti's Agenda
[caption id="attachment_110876" align="alignnone" width="960"] Osisioma Flyover[/caption]
READ ALSO: REAL PICTURES: ROCHAS COLLECTS CERTIFICATE OF RETURN
Read full below:
READ ALSO: Aba's Future: Chief Chinasa Calls on Global Abians to Partner with Governor Otti
Kinetic Abia: Osisioma Flyover will Be Delivered
READ ALSO: A Loyal Force In Abia's Rebirth: Dogo Bende Celebrates Emetu's Leadership And Legacy
The Ikpeazu administration planned to commission Osisioma Flyover on May 29th, 2021, but the finishing suffered two challenges that necessitated the postponement of the already mapped out commissioning programme:
READ ALSO: B00M: How NDLEA Apprehended Former Vice Chairman, Recovers Drugs, Millions | READ DETAILS
The contractors couldn't conclude the work on top and around the bridge because of the necessity to align the project with the ongoing reconstruction of the Osisioma-Asa Nentu segment of Enugu-Port Harcourt Federal Highway which is not within the control of the state government and its contractors.
An "act of GodÔÇØ (force majeure) involving the expatriate supervisor of the project who was involved in a fatal robbery incident in Umuahia that led to the killing of his driver and mobile police security attachee along Mission Hill. The traumatized Chinese whose colleague in another southeast state was also involved in a violent incident around the same period fled the state to Abuja.
It is instructive to note that the state government has fully paid for the flyover project and is working with the federal controller of works in the state to sort out construction delays around the flyover.
The supervisor for the flyover project is also back on site and currently executing finishing works that are not connected to the associated federal project.
The state government appreciates the challenges road users face around the area and is doing everything possible to ensure that the contractors deliver as soon as possible.
READ ALSO: WATCH VIDEO: Naval Officers Dancing, Celebrating Over The Removal Of Former Chief Of Naval Staff
It is also important to note that even if our contractors conclude the earth work on top of the bridge at this moment the bridge will still not be usable without the contiguous federal project being completed.
READ ALSO: Atiku's Camp Faults Afenifere endorsement Of Tinubu
We therefore urge our people to be a little more patient and remain confident that the Ikpeazu administration will continue to do the needful to deliver better life to them.
Thank you.
JOK
READ ALSO: Birthday: Emenike Iroegbu Celebrates Ikechukwu Emetu, Praises His Support for Otti's Agenda
19/08/2021
Related Stories
GRAND RECEPTION: Massive Crowd Endorses Alex Otti for 2027 as He Unveils Bold Plans to Transform Umuahia | WATCH VIDEO
Chimaobi Desmond Anyaso Challenges Youths on Enterprise, Leadership, Backs Continuity of Otti's Reforms
A Loyal Force In Abia's Rebirth: Dogo Bende Celebrates Emetu's Leadership And Legacy
Birthday: Former Deputy Governor Ude Oko Chukwu Celebrates Ikechukwu Emetu, Offers Prayers for Strength in Building New Abia
Birthday: Emenike Iroegbu Celebrates Ikechukwu Emetu, Praises His Support for Otti's Agenda
REVEALED: Bende Youths Declare Total Support for Alex Otti's 2027 Return, Back Chimaobi Desmond Anyaso for Reps Seat
""
— Afnews Editor